Flare

BAAQMD Refinery Flare Emission Report
Report Settings
Tesoro Martinez - Ammonia Plant
Download CSV
April - 2016
Date Vent Gas Flow Methane NMHC Sulfur Dioxide
(mo/day/yr) (volume in scf) See note **** (lbs) (lbs) (lbs)
4/1/2016 27,263.00 0.00 0.00 433.58
4/2/2016 26,399.00 0.00 0.00 0.10
4/3/2016 21,067.00 0.00 0.00 0.09
4/4/2016 14,018.00 0.00 0.00 0.08
4/5/2016 47,633.00 0.00 0.00 0.14
4/6/2016 43,667.00 0.00 0.00 0.13
4/7/2016 23,067.00 0.00 0.00 31.77
4/8/2016 31,838.00 0.00 0.00 12.44
4/9/2016 36,604.00 0.00 0.00 0.12
4/10/2016 37,673.00 0.00 0.00 0.12
4/11/2016 38,465.00 0.00 0.00 0.12
4/12/2016 50,784.00 0.00 0.00 0.14
4/13/2016 7,082.00 0.00 0.00 0.07
4/14/2016 17,891.00 0.00 0.00 0.09
4/15/2016 16,810.00 0.00 0.00 5.04
4/16/2016 12,449.00 0.00 0.00 0.08
4/17/2016 20,104.00 0.00 0.00 0.09
4/18/2016 32,681.00 0.00 0.00 0.11
4/19/2016 27,534.00 0.00 0.00 0.10
4/20/2016 71,179.00 0.00 0.00 74.01
4/21/2016 35,303.00 0.00 0.00 0.12
4/22/2016 48,663.00 0.00 0.00 0.14
4/23/2016 37,967.00 0.00 0.00 0.12
4/24/2016 35,638.00 0.00 0.00 0.12
4/25/2016 58,516.00 0.00 0.00 0.16
4/26/2016 84,449.00 0.00 0.00 0.20
4/27/2016 92,234.00 0.00 0.00 0.21
4/28/2016 38,063.00 0.00 0.00 0.12
4/29/2016 33,123.00 0.00 0.00 0.11
4/30/2016 74,189.00 0.00 0.00 0.18
April Totals 1,142,353.00 0.00 0.00 559.90
  • * Natural gas is used for both pilot and purge gas for the refinery flare system, except for the Emergency Flare that uses nitrogen as purge gas.
    The flow is determined using an orifice calculation based on the orifice size in the lines and the line pressure upstream of the orifice.
    ** The purge gas and pilot gas flows at the Ammonia Plant flare are measured by rotameters in the natural
    gas and nitrogen lines.
    *** The purge gas and pilot gas flows at the 50 Unit flare are measured by flow meters
    **** Corrected for seal pot level and pressure data
    ***** 50 Unit change in flare purge gas to nitrogen
    In the case of an invalid sample, the monthly average was used for composition data
Tesoro Martinez Ammonia Plant Flare Report 4/1/2016 - 4/30/2016
 
 

Contact Us

Communications
General Information

415.749.4900

Meteorology & Measurements
Air Monitoring

415.749.4985

Contact Us

Spare the Air Status

Last Updated: 4/13/2023