This is the Preliminary Determination of Compliance (PDOC) for the Tesla Power Project (TPP), an 1140-MW, natural-gas fired, combined-cycle merchant power plant proposed by Midway Power, LLC. The power plant will be located at the northeastern edge of Alameda County and will be composed of four nominal 160-MW General Electric 7FA combustion gas turbines, four heat recovery steam generators equipped with 272.2 MM BTU/hr duct burners and two 250-MW steam turbine generators. The facility will also include two exempt 11-cell cooling towers and a 368-hp fire pump diesel engine.
All documents are in Adobe.pdf format.
|