Búsqueda

  • SMOP Final Evaluation
    SMOP Final Evaluation

    may. 3, 2023 ... ENGINEERING EVALUATION Vantage Data Centers Management Co., LLC Application: 28827 Plant: 20295 2820 Northwestern Parkway, Santa Clara, CA 95051 BACKGROUND Vantage Data Centers Management ...

    Read More
    (447 Kb PDF, 19 pgs)

    may. 3, 2023 ... ENGINEERING EVALUATION Vantage Data Centers Management Co., LLC Application: 28827 Plant: 20295 2820 Northwestern Parkway, Santa Clara, CA 95051 BACKGROUND Vantage Data Centers Management ...

  • 31986 Permit Evaluation
    31986 Permit Evaluation

    Jul 25, 2023 ... ENGINEERING EVALUATION REPORT AMAZON DATA SERVICES INC PLANT #25018 APPLICATION #31986 BACKGROUND Amazon Data Services Inc (Applicant) currently operates a data center at 25800 Clawiter ...

    Read More
    (556 Kb PDF, 29 pgs)

    Jul 25, 2023 ... ENGINEERING EVALUATION REPORT AMAZON DATA SERVICES INC PLANT #25018 APPLICATION #31986 BACKGROUND Amazon Data Services Inc (Applicant) currently operates a data center at 25800 Clawiter ...

  • 25701 Permit Evaluation
    25701 Permit Evaluation

    mar. 14, 2014 ... ENGINEERING EVALUATION Mercy Housing California 50, LP Application: 25701 Plant: 22097 BACKGROUND Mercy Housing California 50, LP has applied to obtain an Authority to Construct (AC) ...

    Read More
    (311 Kb PDF, 8 pgs)

    mar. 14, 2014 ... ENGINEERING EVALUATION Mercy Housing California 50, LP Application: 25701 Plant: 22097 BACKGROUND Mercy Housing California 50, LP has applied to obtain an Authority to Construct (AC) ...

  • Regulation 9, Rule 7 DRAFT Amendments
    Regulation 9, Rule 7 DRAFT Amendments

    mar. 16, 2011 ... DRAFT 3-17-2011 REGULATION 9 INORGANIC GASEOUS POLLUTANTS RULE 7 NITROGEN OXIDES AND CARBON MONOXIDE FROM INDUSTRIAL, INSTITUTIONAL, AND COMMERCIAL BOILERS, STEAM GENERATORS, AND PROCESS ...

    Read More
    (143 Kb PDF, 15 pgs)

    mar. 16, 2011 ... DRAFT 3-17-2011 REGULATION 9 INORGANIC GASEOUS POLLUTANTS RULE 7 NITROGEN OXIDES AND CARBON MONOXIDE FROM INDUSTRIAL, INSTITUTIONAL, AND COMMERCIAL BOILERS, STEAM GENERATORS, AND PROCESS ...

  • Table C1 2
    Table C1 2

    Mar 19, 2014 ... Table C1-2: Boiler NOx Control Cost Calculations Boiler Hrs of Heat LNB/FGR/SCR Annual Operating Costs Total Capacity Operation Release Cost NH3 FGR (MMBtu/hr) (hr/yr) (MMBtu/yr) Annualized SCR ...

    Read More
    (231 Kb PDF, 3 pgs)

    Mar 19, 2014 ... Table C1-2: Boiler NOx Control Cost Calculations Boiler Hrs of Heat LNB/FGR/SCR Annual Operating Costs Total Capacity Operation Release Cost NH3 FGR (MMBtu/hr) (hr/yr) (MMBtu/yr) Annualized SCR ...

  • Current Permit
    Current Permit

    Apr 26, 2006 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Final MAJOR FACILITY REVIEW PERMIT Issued To: Redwood Landfill, Inc. Facility ...

    Read More
    (455 Kb PDF, 138 pgs)

    Apr 26, 2006 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Final MAJOR FACILITY REVIEW PERMIT Issued To: Redwood Landfill, Inc. Facility ...

  • Current Permit
    Current Permit

    Dec 29, 2005 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Final MAJOR FACILITY REVIEW PERMIT Issued To: Redwood Landfill, Inc. Facility ...

    Read More
    (455 Kb PDF, 136 pgs)

    Dec 29, 2005 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Final MAJOR FACILITY REVIEW PERMIT Issued To: Redwood Landfill, Inc. Facility ...

  • Committee Presentations
    Committee Presentations

    Mar 20, 2014 ... AGENDA: 4 10-Point Climate Action Work Program Climate Protection Committee March 20, 2014 Henry Hilken Director, Planning, Rules & Research ...

    Read More
    (2 Mb PDF, 31 pgs)

    Mar 20, 2014 ... AGENDA: 4 10-Point Climate Action Work Program Climate Protection Committee March 20, 2014 Henry Hilken Director, Planning, Rules & Research ...

  • Board Agenda
    Board Agenda

    abr. 30, 2020 ... SPECIAL MEETING OF THE BOARD OF DIRECTORS BUDGET HEARING May 6, 2020 THIS MEETING WILL BE CONDUCTED UNDER PROCEDURES AUTHORIZED BY EXECUTIVE ...

    Read More
    (5 Mb PDF, 215 pgs)

    abr. 30, 2020 ... SPECIAL MEETING OF THE BOARD OF DIRECTORS BUDGET HEARING May 6, 2020 THIS MEETING WILL BE CONDUCTED UNDER PROCEDURES AUTHORIZED BY EXECUTIVE ...

  • Statement of Basis
    Statement of Basis

    Jul 18, 2012 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Permit Evaluation and Statement of Basis for RENEWAL of MAJOR FACILITY REVIEW ...

    Read More
    (619 Kb PDF, 33 pgs)

    Jul 18, 2012 ... Bay Area Air Quality Management District 939 Ellis Street San Francisco, CA 94109 (415) 771-6000 Permit Evaluation and Statement of Basis for RENEWAL of MAJOR FACILITY REVIEW ...

  • 28434 Permit Evaluation
    28434 Permit Evaluation

    abr. 25, 2017 ... PRELIMINARY ENGINEERING EVALUATION Solano County Transit Operations, Plant: 6426 Application: 28434 BACKGROUND The Solano County Transit Operations has applied to obtain an Authority to ...

    Read More
    (379 Kb PDF, 9 pgs)

    abr. 25, 2017 ... PRELIMINARY ENGINEERING EVALUATION Solano County Transit Operations, Plant: 6426 Application: 28434 BACKGROUND The Solano County Transit Operations has applied to obtain an Authority to ...

  • 26515 Permit Evaluation
    26515 Permit Evaluation

    dic. 1, 2014 ... Engineering Evaluation Report Verint Application #26515; Plant # 22586 1. BACKGROUND This application is for a Permit to Operate a 2014, 755 Bhp diesel engine that is used as a driver for ...

    Read More
    (364 Kb PDF, 11 pgs)

    dic. 1, 2014 ... Engineering Evaluation Report Verint Application #26515; Plant # 22586 1. BACKGROUND This application is for a Permit to Operate a 2014, 755 Bhp diesel engine that is used as a driver for ...

  • CCEEB Comments
    CCEEB Comments

    dic. 2, 2016 ... December  2,  2016     Mr.  Victor  Douglas   BAAQMD   375  Beale  Street,  Suite  600   San  Francisco,  CA  94105     RE:   Proposed ...

    Read More
    (207 Kb PDF, 7 pgs)

    dic. 2, 2016 ... December  2,  2016     Mr.  Victor  Douglas   BAAQMD   375  Beale  Street,  Suite  600   San  Francisco,  CA  94105     RE:   Proposed ...

  • Semi-Annual Monitoring Report 2022 A
    Semi-Annual Monitoring Report 2022 A

    Mar 30, 2023 ... ' ., . .: ~ f • RECEIVED 2023 KAR 21 PM t2: 1, BAY AREA AlR OU,\LITY MAHi\GEMEHT DlS'fRIC f ÎRANSMONTAIGNE ~-.;- March 22, 2023 UPS Tracking#: lZ 1 VO 21 V 02 9928 6678 Director of Compliance ...

    Read More
    (19 Mb PDF, 50 pgs)

    Mar 30, 2023 ... ' ., . .: ~ f • RECEIVED 2023 KAR 21 PM t2: 1, BAY AREA AlR OU,\LITY MAHi\GEMEHT DlS'fRIC f ÎRANSMONTAIGNE ~-.;- March 22, 2023 UPS Tracking#: lZ 1 VO 21 V 02 9928 6678 Director of Compliance ...

  • Semi-Annual Monitoring Report 2021 B
    Semi-Annual Monitoring Report 2021 B

    oct. 11, 2022 ... , . ,. : ~ï • I TRANSMONTAIGNE UPS Tracking#: lZ lVO 21V 02 9262 6358 September 23, 2022 Director of Compliance and Enforcement Bay Area Air Quality Management District Attention: Title V ...

    Read More
    (19 Mb PDF, 50 pgs)

    oct. 11, 2022 ... , . ,. : ~ï • I TRANSMONTAIGNE UPS Tracking#: lZ lVO 21V 02 9262 6358 September 23, 2022 Director of Compliance and Enforcement Bay Area Air Quality Management District Attention: Title V ...

  • Committee Agenda
    Committee Agenda

    Mar 11, 2021 ... BOARD OF DIRECTORS ADMINISTRATION COMMITTEE COMMITTEE MEMBERS CINDY CHAVEZ – CO CHAIR CAROLE GROOM – CO CHAIR KAREN MITCHOFF – VICE CHAIR MARGARET ABE-KOGA JOHN BAUTERS RICH ...

    Read More
    (4 Mb PDF, 270 pgs)

    Mar 11, 2021 ... BOARD OF DIRECTORS ADMINISTRATION COMMITTEE COMMITTEE MEMBERS CINDY CHAVEZ – CO CHAIR CAROLE GROOM – CO CHAIR KAREN MITCHOFF – VICE CHAIR MARGARET ABE-KOGA JOHN BAUTERS RICH ...

  • 26870 Permit Evaluation
    26870 Permit Evaluation

    jul. 9, 2015 ... ENGINEERING EVALUATION San Mateo Event Center Application: 26870 Plant: 22852 2495 South Delaware Street, San Mateo, CA 94403 BACKGROUND San Mateo Event Center has applied to obtain an ...

    Read More
    (181 Kb PDF, 14 pgs)

    jul. 9, 2015 ... ENGINEERING EVALUATION San Mateo Event Center Application: 26870 Plant: 22852 2495 South Delaware Street, San Mateo, CA 94403 BACKGROUND San Mateo Event Center has applied to obtain an ...

  • Semi-Annual Monitoring Report 2019 B
    Semi-Annual Monitoring Report 2019 B

    nov. 3, 2020 ... r-'-:r:.'.'i'r-n I! ;. .. __. ~.·t .• l e:: ....... ....., 2C20 SEP 3 O PM !2: I ti 1,-,1 ri~'./ ,. "':'"" ,I\ :\ '~ ~·~ • ~ O:, î t·\i\L J"\ r , i L \J.- : __ i ! : ,, '· . ! .r· :- ~ . • ~.

    Read More
    (22 Mb PDF, 50 pgs)

    nov. 3, 2020 ... r-'-:r:.'.'i'r-n I! ;. .. __. ~.·t .• l e:: ....... ....., 2C20 SEP 3 O PM !2: I ti 1,-,1 ri~'./ ,. "':'"" ,I\ :\ '~ ~·~ • ~ O:, î t·\i\L J"\ r , i L \J.- : __ i ! : ,, '· . ! .r· :- ~ . • ~.

Spare the Air Status