Regulation 2 Rule 1: General Requirements

The Air District is evaluating potential changes to Rules 2-1 and 2-5. For more information, please visit the Regulation 2 Amendments web page.

Amendments to Regulation 2, Rule 1: Permits - General Requirements were adopted by the Air District's Board of Directors at a public hearing on December 6, 2017:

The Air District developed revisions to its permitting programs through amendments to Regulation 2, Rule 1: Permits - General Requirements. The amendments to this rule were developed and adopted along with other changes to the permits regulation. Amendments to Rule 2-1, along with amendments to Rule 2-2, Rule 2-4, and Rule 2-6, made significant changes to the New Source Review pre-construction permit program and the Title V Major Facility Review operating permit program. All information on the rule development process for the amendments to Rules 2-1, 2-2, 2-4, and 2-6 can be found on the Permit Regulations Changes page.

 Rule #Rule NameAdoptedAmendedtable-mobile-only-column
Regulation 2, Rule 1General Requirements1/1/198012/5/2017
Adopted
Document:
Description:
Includes criteria for issuance or denial of permits, exemptions, appeals against decisions of the APCO and District actions on applications.
Rule #:
Regulation 2, Rule 1
Rule Name:
General Requirements
Adopted:
1/1/1980
Amended:
12/5/2017
Contact:
  • Engineering
  • General Engineering Information
  • 415.749.4990
 

Rule Status

Adopted

Document

Amended Regulation 2, Rule 1: Permits – General Requirements

Contact

  • Engineering
  • General Engineering Information
  • 415.749.4990

Description

Includes criteria for issuance or denial of permits, exemptions, appeals against decisions of the APCO and District actions on applications.

Spare the Air Status

Last Updated: 7/22/2021