Advisory
|
Valero Refinery in Benicia notified the Air District of ongoing flaring due to a planned shutdown of refinery equipment. Air District inspectors will be closely monitoring. Report air quality complaints: 800-334-ODOR or online.
|
|
|
|
|
249 results for 'Report'
Search: 'Report'
249 Search:
Sep 18, 2019 ... Attachment III Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events May 7, 2019 Sudden Change in Hydrogen Demand ...
Read MoreSep 18, 2019 ... Attachment III Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events May 7, 2019 Sudden Change in Hydrogen Demand ...
Apr 30, 2024 ... BAAQMD received 04/30/24 PHILLIPS 66 RODEO RENEWABLE ENERGY COMPLEX 1380 San Pablo Avenue Rodeo, CA 94572 April 30, 2024 154-ESDR-24 02-E-01-B Via E-Mail at Compliance@BAAQMD.gov Mail Stop FM1 ...
Read MoreApr 30, 2024 ... BAAQMD received 04/30/24 PHILLIPS 66 RODEO RENEWABLE ENERGY COMPLEX 1380 San Pablo Avenue Rodeo, CA 94572 April 30, 2024 154-ESDR-24 02-E-01-B Via E-Mail at Compliance@BAAQMD.gov Mail Stop FM1 ...
Hul 1, 2019 ... Chevron Q1 Shawn Lee HES Manager, Richmond Refinery April 29, 2019 Bay Area Air Quality Management District Mail Stop FM 1 375 Beale Street, Suite 600 San Francisco, CA 94105 Chevron ...
Read MoreHul 1, 2019 ... Chevron Q1 Shawn Lee HES Manager, Richmond Refinery April 29, 2019 Bay Area Air Quality Management District Mail Stop FM 1 375 Beale Street, Suite 600 San Francisco, CA 94105 Chevron ...
Oct 30, 2024 ... BAAQMD received on 10/30/24 FLARE CAUSAL ANALYSIS REPORT 1. Date on which the report was drafted: October 28, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3. The ...
Read MoreOct 30, 2024 ... BAAQMD received on 10/30/24 FLARE CAUSAL ANALYSIS REPORT 1. Date on which the report was drafted: October 28, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3. The ...
Jul 26, 2024 ... BAAQMD received on 07/26/24 Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events May 23 - 24, 2024 Flaring Due to Shutdown of Hydrogen Plant Trains ...
Read MoreJul 26, 2024 ... BAAQMD received on 07/26/24 Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events May 23 - 24, 2024 Flaring Due to Shutdown of Hydrogen Plant Trains ...
May 30, 2024 ... BAAQMD received 05/30/24 PHILLIPS 66 RODEO RENEWABLE ENERGY COMPLEX 1380 San Pablo Avenue Rodeo, CA 94572 May 30, 2024 190-ESDR-24 02-E-01-B Via E-Mail at Compliance@BAAQMD.gov Mail Stop FM1 ...
Read MoreMay 30, 2024 ... BAAQMD received 05/30/24 PHILLIPS 66 RODEO RENEWABLE ENERGY COMPLEX 1380 San Pablo Avenue Rodeo, CA 94572 May 30, 2024 190-ESDR-24 02-E-01-B Via E-Mail at Compliance@BAAQMD.gov Mail Stop FM1 ...
Hul 1, 2019 ... Attachment IV Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events February 24, 2019 Pressure Safety Valve Malfunction in the TKC Unit ...
Read MoreHul 1, 2019 ... Attachment IV Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events February 24, 2019 Pressure Safety Valve Malfunction in the TKC Unit ...
Nov 19, 2024 ... BAAQMD received on 11/22/24 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: November 19, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3.
Read MoreNov 19, 2024 ... BAAQMD received on 11/22/24 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: November 19, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3.
Oct 30, 2024 ... BAAQMD received on 10/30/24 Attachment I Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events August 02, 2024 Flaring Due to Mechanical Failure of Compressor Steam System ...
Read MoreOct 30, 2024 ... BAAQMD received on 10/30/24 Attachment I Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events August 02, 2024 Flaring Due to Mechanical Failure of Compressor Steam System ...
Mar 11, 2024 ... BAAQMD received on 03/11/24 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: March 5, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3. The ...
Read MoreMar 11, 2024 ... BAAQMD received on 03/11/24 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: March 5, 2024 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3. The ...
Apr 18, 2019 ... Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events January 4, 2019 - January 7, 2019 Start-up and Shutdown of Hydrogen Plant Train 2 (S-4450) ...
Read MoreApr 18, 2019 ... Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events January 4, 2019 - January 7, 2019 Start-up and Shutdown of Hydrogen Plant Train 2 (S-4450) ...
Jul 1, 2019 ... Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events February 2-6, 2019 Start-up of Hydrogen Plant Train 2 (S-4450) ...
Read MoreJul 1, 2019 ... Attachment II Causal Analysis Report Chevron Richmond Refinery Reportable Flaring Events February 2-6, 2019 Start-up of Hydrogen Plant Train 2 (S-4450) ...
Oct 29, 2025 ... BAAQMD received on 10/29/25 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: October 27, 2025 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3.
Read MoreOct 29, 2025 ... BAAQMD received on 10/29/25 FLARE CAUSAL ANALYSIS REPORT - PUBLIC 1. Date on which the report was drafted: October 27, 2025 2. The refinery name and site number. Martinez Refinery, Plant # B2758 3.